Thakurgaon Sadar
BSCIC Food Processing Industrial Estate
Whole programme; the Thakurgaon share is not established.
The evidenced situation
Reported expenditure: ৳482,872,000 · 30 June 2025
Evidence needed · Delivery date unknown
Payment and present condition remain separate questions.
BSCIC Food Processing Industrial Estate · Questions, observations & replies
Loading source developments…
Cost by part
2 rowsPlanned estimate · not spending or paymentWhole programme; the Thakurgaon share is not established.
Same full project title; no printed project-code match.
Construction of Boundary wall2,138.78 metresAlso in the 2025-2026 plan৳12.86 crore
- Exact amount
- ৳128,607,000
- Stage
- Planned
- Quantity
- 2,138.78 metres · unit in source: meter
The same name, quantity and amount are also in the 2025-2026 plan. It may be the same work planned again; do not add the two.
Procurement plan for FY 2024-2025; APP 204813, package 1078286, PKG/DEV/Thakurgaon/EGP-02/2024-25; retained 28 July 2026.
Bar length compares each row with the largest row in this list. It is not a share or percentage of any total.
What these amounts are
The amount is the entire planned lot estimate, not a unit rate, award or payment. Versions/retenders may overlap; do not sum repeated work. Source unit is retained literally.
The source gives no unit rates; none has been worked out by dividing a total.
Each row is as the source gives it. Rows are not added into a total.
Where the money is
Each step is a separate stage; amounts are never added together.
Estimate or approved cost
৳116.73 croreApproved project cost · ৳1,167,300,000 · Date not known · Whole projectWhat this figure is
From the FY2025–26 ADP edition; current revisions may differ.
Allocation
৳20.6 croreAnnual allocation · ৳206,000,000 · Date not known · 2026-27What this figure is
These are whole-programme figures, not Thakurgaon allocations, releases, paid bills or available cash. Spending through June 2025 cannot be subtracted from the 2026–27 allocation to calculate a remaining balance.
Funds released
Record not obtained · unknown is not zero
Contract
Record not obtainedSpending in a report
৳48.29 croreReported expenditure · ৳482,872,000 · 30 June 2025 · through 2025-06-30What this figure is
These are whole-programme figures, not Thakurgaon allocations, releases, paid bills or available cash. Spending through June 2025 cannot be subtracted from the 2026–27 allocation to calculate a remaining balance.
Certified bill
Record not obtained · unknown is not zero
Payment made
Record not obtained · unknown is not zero
What happened when
Project start in source
Source reportProject end in source
Source reportAdmin-building contract signed
Contract recordToday
A date in a report or certificate is not an inspection.
Who answers for it
What you can do
For safety, keep faces, house numbers and phone numbers out of photos and posts.
Full account and evidence
Every figure, date and document with its source. Open a topic to check it.
Every amount and its source
10 sourced amounts · 4 stages not collected
Separate financial stages · never added together
- Reported expenditure৳482,872,00030 June 2025 · through 2025-06-30
These are whole-programme figures, not Thakurgaon allocations, releases, paid bills or available cash. Spending through June 2025 cannot be subtracted from the 2026–27 allocation to calculate a remaining balance.
- Approved project cost৳1,167,300,000Reporting date unknown · Whole project
From the FY2025–26 ADP edition; current revisions may differ.
- Allocation৳200,000,000Reporting date unknown · 2025-2026
From the FY2025–26 ADP edition; current revisions may differ.
- Reported expenditure৳478,200,0002024-06
Reported revenue and capital expenditure combined; this is a historical cumulative figure.
- Approved project cost৳1,167,301,000Reporting date unknown · whole project
These are whole-programme figures, not Thakurgaon allocations, releases, paid bills or available cash. Spending through June 2025 cannot be subtracted from the 2026–27 allocation to calculate a remaining balance.
- Revised annual allocation৳146,000,000Reporting date unknown · 2025-26
These are whole-programme figures, not Thakurgaon allocations, releases, paid bills or available cash. Spending through June 2025 cannot be subtracted from the 2026–27 allocation to calculate a remaining balance.
- Annual allocation৳206,000,000Reporting date unknown · 2026-27
These are whole-programme figures, not Thakurgaon allocations, releases, paid bills or available cash. Spending through June 2025 cannot be subtracted from the 2026–27 allocation to calculate a remaining balance.
- FY2026–27 revenue allocation৳6,000,000Reporting date unknown · 2026-27
FY2026–27 whole-project allocation category, not expenditure, release or payment. Revenue and capital are components of the already displayed annual allocation, not additional money.
- FY2026–27 capital allocation৳200,000,000Reporting date unknown · 2026-27
Same limits as FY2026–27 revenue allocation above.
- Admin-building package: awarded commitment৳30,917,804.4924 October 2026
Award commitment for this administrative-building package only, not whole-project spending, an executed payment, a complete signed contract bundle or verified worksite. The public notice supplies the exact project code through tender 1313930.
Not collectedExecuted paymentsDated cash balanceFunds releasedCertified bills
- Executed payments Payment records not collected.
- Dated cash balance Annual allocation minus cumulative expenditure is not a valid cash balance.
- Funds released The required evidence has not been collected. Unknown does not mean zero.
- Certified bills The required evidence has not been collected. Unknown does not mean zero.
Payment ledger incompleteCash balance unknown
Unknown payments are not zero. Differences between financial stages do not establish unspent or missing money. A comparable ledger and reconciliation are needed for a balance.
Dates in the records
3 dated entries
Project start in source Source reported
A dated source report, not an independent inspection, acceptance or executed-payment record.Project end in source Source reported
A dated source report, not an independent inspection, acceptance or executed-payment record.Admin-building contract signed Contract record
Award commitment for this administrative-building package only, not whole-project spending, an executed payment, a complete signed contract bundle or verified worksite. The public notice supplies the exact project code through tender 1313930.Report date: 4 October 2026
A completed date field or certificate claim does not establish independent acceptance. An actual start or completion date is only identified when the source establishes it.
Work reports
Tender 1321867, published 1 October 2026; exact project 224351000 / APP 227888. No award or payment has been established from this notice. · acceptance unverified
- RCC drainage tender noticeTender 1321867, published 1 October 2026; exact project 224351000 / APP 227888. No award or payment has been established from this notice.
1 October 2026 · A retained procurement notice, separate from the existing awarded contracts and annual project allocation.
- Dumping yard tender noticeTender 1321868, published 1 October 2026; exact project 224351000 / APP 227888. No award or payment has been established from this notice.
1 October 2026 · A retained procurement notice, separate from the existing awarded contracts and annual project allocation.
Independent acceptance and the present condition are not established here. A dated resident observation appears in the conversation as a citizen account.
Scope & responsibility
A project account
These are whole-programme figures, not Thakurgaon allocations, releases, paid bills or available cash. Spending through June 2025 cannot be subtracted from the 2026–27 allocation to calculate a remaining balance.
- Responsible office in source
- Bangladesh Small and Cottage Industries Corporation
- Record
- project-224351000 · reviewed 6 October 2026
Location is recorded in the source; current conditions have not been independently inspected.
Original record title
BSCIC Food Processing Industrial Estate, Thakurgaon (1st Revised)
Record details
Identifiers, procurement and bids
Planned quantities are separate from measured or accepted work.
Record and package identifiers
- Project code
- 224351000
Funding and procurement
- Funding
- GoB
- Approval in this edition
- Approved in this ADP edition
Other reported fields
- Administrative-building award held
- Tender 1313930: award BDT 30,917,804.492 to Noor Hossain Limited; signed 4 October 2026. The public notice gives tentative package dates of 16 September 2026–15 April 2027.4 October 2026 · Award commitment for this administrative-building package only, not whole-project spending, an executed payment, a complete signed contract bundle or verified worksite. The public notice supplies the exact project code through tender 1313930.
Differences & limits
4 points to check
These are questions to check. Missing records, money differences and reported completion do not establish corruption.
- FY2025-26 allocation and expenditure through June2024 are different periods. These records do not establish current spending, releases, contractor payments, or money left.
- Selected approved ADP entry, not a complete district ADP census.
- The book marks this project with an asterisk: funds may not be released or spent without extending its implementation period. Any later extension is not established here.
- New procurement notices do not resolve the FY2026–27 ADP condition requiring an approved project-period extension. The extension order and release clearance remain uncollected.
Missing documents
5 records · who holds them
Some answers are shown here, and some held documents still need further extraction or review. Other records need a request to the holding office. The labels distinguish these situations; missing online does not mean unobtainable.
Office holding all of these: BSCIC project director and Thakurgaon district office; project finance/accounts
Approved scope and item prices
Partly answeredPlans and award summaries exist. Tender 1313930 is publicly marked ContractAwarded; its complete priced contract has not been obtained.
See the evidence for this topic3 fields reviewed · 6 October 2026
What the sources establish
Evidence held- What we found
- The award detail for tender 1313930 is held: BDT 30,917,804.492, Noor Hossain Limited, signed 4 October 2026. Seven related APP plans provide planned quantities. The complete signed priced BOQ is still not collected.
Read the source date and scope with this finding. A retrieved summary is not the underlying signed account.
Approved scope and item prices
Ask the holding office- What we found
- Request the existing records from the responsible office. Ask it to confirm records not yet created or held elsewhere.
- Still needed
- Signed scope, specifications, drawings and priced BOQ: item, quantity, unit, accepted rate and total.
- Holding office
- BSCIC project director and Thakurgaon district office; project finance/accounts
The named office is a collection route; custody, existence and disclosure of each missing file require confirmation. Missing records do not establish wrongdoing.
Tender document access
Access needs another route- What we found
- The reviewed document page requires registered-user access. The public notice remains available.
- Holding office
- BSCIC project director and Thakurgaon district office; project finance/accounts
This is an observed access condition, not proof that an office copy is unavailable.
Checked:
Start and approved changes
Partly answeredNew package dates extend into 2027. They do not prove approval of an extension for the entire project.
See the evidence for this topic2 fields reviewed · 6 October 2026
What the sources establish
Evidence held- What we found
- New package dates extend into 2027. They do not prove approval of an extension for the entire project.
Read the source date and scope with this finding. A retrieved summary is not the underlying signed account.
Start and approved changes
Ask the holding office- What we found
- Request the existing records from the responsible office. Ask it to confirm records not yet created or held elsewhere.
- Still needed
- Signed work order, possession/commencement record and approved time/cost/scope changes with dates and authority.
- Holding office
- BSCIC project director and Thakurgaon district office; project finance/accounts
The named office is a collection route; custody, existence and disclosure of each missing file require confirmation. Missing records do not establish wrongdoing.
Measured work and acceptance
Partly answeredPublic project photos provide context, not dated measured progress or signed acceptance.
See the evidence for this topic2 fields reviewed · 6 October 2026
What the sources establish
Evidence held- What we found
- Public project photos provide context, not dated measured progress or signed acceptance.
Read the source date and scope with this finding. A retrieved summary is not the underlying signed account.
Checked:Measured work and acceptance
Ask the holding office- What we found
- Request the existing records from the responsible office. Ask it to confirm records not yet created or held elsewhere.
- Still needed
- Measurement-book pages, inspection/test reports, defect corrections and any signed acceptance/handover already issued.
- Holding office
- BSCIC project director and Thakurgaon district office; project finance/accounts
The named office is a collection route; custody, existence and disclosure of each missing file require confirmation. Missing records do not establish wrongdoing.
Checked:
Bills and deductions
Partly answeredBudget and reported spending summaries exist. Interim bills, deductions and supporting measurement pages were not obtained.
See the evidence for this topic2 fields reviewed · 6 October 2026
What the sources establish
Evidence held- What we found
- Budget and reported spending summaries exist. Interim bills, deductions and supporting measurement pages were not obtained.
Read the source date and scope with this finding. A retrieved summary is not the underlying signed account.
Checked:Bills and deductions
Ask the holding office- What we found
- Request the existing records from the responsible office. Ask it to confirm records not yet created or held elsewhere.
- Still needed
- Bill register and each certified bill: measured quantities, gross/net amounts, tax, VAT, retention, advances and adjustments.
- Holding office
- BSCIC project director and Thakurgaon district office; project finance/accounts
The named office is a collection route; custody, existence and disclosure of each missing file require confirmation. Missing records do not establish wrongdoing.
Checked:
Payments and account reconciliation
Ask the holding officeAllocation and reported expenditure do not show releases received, individual settlements or project cash balances.
See the evidence for this topic2 fields reviewed · 6 October 2026
What the sources establish
Evidence held- What we found
- Allocation and reported expenditure do not show releases received, individual settlements or project cash balances.
Read the source date and scope with this finding. A retrieved summary is not the underlying signed account.
Checked:Payments and account reconciliation
Ask the holding office- What we found
- Request the existing records from the responsible office. Ask it to confirm records not yet created or held elsewhere.
- Still needed
- Dated release receipts and bill-linked executed settlements, payee/reference, reversals, liabilities and reconciliation for a stated account and cutoff.
- Holding office
- BSCIC project director and Thakurgaon district office; project finance/accounts
The named office is a collection route; custody, existence and disclosure of each missing file require confirmation. Missing records do not establish wrongdoing.
Checked:
Related records
14 connections · exact and possible matches
Exact identifiers and possible matches remain distinct, and a programme total is not this work’s share.
Awarded contracts4 connections
Contract amounts belong to their own packages. They are not additional project spending.
Identifier matchedcontract-130455
Exact project code; award and programme budget are not additive
Identifier matchedcontract-81020
Exact project code; award and programme budget are not additive
Construction of Industrial Boundary Gate 04-Aug-2026 14:10
Identifier matchedcontract-2692506
Exact project code; award and programme budget are not additive
Admin building — Noor Hossain Limited
Identifier matchedcontract-2700351
Exact tender 1313930 in held award detail and public notice; notice prints project code 224351000. Package-lot 2083235. This joins award identity, not actual payment or worksite verification.
Procurement plans7 connections
Planned purchases and quantities. A plan does not prove an award, delivery or payment.
Construction of Office/Admin Building
Possible match · needs reviewplan-711513
The APP row prints the same full project title; APP 217695, package 1239472, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-711515
The APP row prints the same full project title; APP 217695, package 1239505, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-711516
The APP row prints the same full project title; APP 217695, package 1239523, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-1529838
The APP row prints the same full project title; APP 204813, package 1077769, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-1529839
The APP row prints the same full project title; APP 204813, package 1078286, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-1907938
The APP row prints the same full project title; APP 227888, package 1416125, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Construction RCC Drain of Industrial Estate
Possible match · needs reviewplan-1907939
The APP row prints the same full project title; APP 227888, package 1416133, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Tender notices2 connections
Published procurement notices; any later award has its own evidence.
Construction of RCC Drain and culvert
Identifier matchedtender-1321867
Retained notice prints exact project code 224351000 and APP 227888. Notice is not an award or payment.
Identifier matchedtender-1321868
Retained notice prints exact project code 224351000 and APP 227888. Notice is not an award or payment.
Programmes and other records1 connections
Read each connection’s basis and scope before comparing amounts.
Same project code in another retained record
Identifier matchedprogramme-224351000
Exact project code; versions and amounts are not additive