Thakurgaon Sadar
The Thakurgaon college component only.
Administrative-building contract value in report: ৳163,165,900 · Date not known
50% · June 2026
Payment and present condition remain separate questions.
Thakurgaon engineering college: building, time and inspection · Questions, observations & replies
Loading source developments…
Each step is a separate stage; amounts are never added together.
Estimate or approved cost
৳18.13 croreAdministrative-building estimate in report · ৳181,308,000 · Date not known · Report table 3.6, Thakurgaon W-08A source-reported amount, not independently verified executed payments. Do not add cumulative and annual figures, or components and their totals.
Funds released
Record not obtained · unknown is not zero
Contract
৳16.32 croreAdministrative-building contract value in report · ৳163,165,900 · Date not known · Report table 3.6, Thakurgaon W-08As printed: 1,631.659 lakh = BDT 163,165,900. This differs from the candidate e-GP award BDT 163,177,531.659. No variation or payment inferred.
Spending in a report
Record not obtainedCertified bill
Record not obtained · unknown is not zero
Payment made
Record not obtained · unknown is not zero
Spending as the source reports it · not proof of paymentThe Thakurgaon college component only.
Reported Thakurgaon land-acquisition amount, separate from the administrative-building contract. The table says paid, but no payee-level compensation ledger, voucher or executed settlement reference is held. It is not the building expenditure headline.
Each row is as the source gives it. Rows are not added into a total.
Land-acquisition letter to Deputy Commissioner
Source reportReported land handover to EED
Source reportSource schedule start — disputed
Source reportIMED-reported field inspection
Source reportDate under completion heading — unverified
Source reportSource schedule finish — disputed
Source reportToday
A date in a report or certificate is not an inspection.
For safety, keep faces, house numbers and phone numbers out of photos and posts.
Every figure, date and document with its source. Open a topic to check it.
Separate financial stages · never added together
As printed: 1,631.659 lakh = BDT 163,165,900. This differs from the candidate e-GP award BDT 163,177,531.659. No variation or payment inferred.
A source-reported amount, not independently verified executed payments. Do not add cumulative and annual figures, or components and their totals.
The required evidence has not been collected. Unknown does not mean zero.
Payment ledger incompleteCash balance unknown
Unknown payments are not zero. Differences between financial stages do not establish unspent or missing money. A comparable ledger and reconciliation are needed for a balance.
Land-acquisition letter to Deputy Commissioner Source reported
The date is reported in IMED table 3.4. The original letter/handover instrument is not held; it concerns land, not building commencement or acceptance.Reported land handover to EED Source reported
The date is reported in IMED table 3.4. The original letter/handover instrument is not held; it concerns land, not building commencement or acceptance.Source schedule start — disputed Source reported
Disputed source date only. IMED dates conflict internally and with the candidate award; 50% progress and ongoing works prevent treating the completion heading as actual completion. Do not calculate an established delay from these fields.Date under completion heading — unverified Source reported
Disputed source date only. IMED dates conflict internally and with the candidate award; 50% progress and ongoing works prevent treating the completion heading as actual completion. Do not calculate an established delay from these fields.Source schedule finish — disputed Source reported
Disputed source date only. IMED dates conflict internally and with the candidate award; 50% progress and ongoing works prevent treating the completion heading as actual completion. Do not calculate an established delay from these fields.A completed date field or certificate claim does not establish independent acceptance. An actual start or completion date is only identified when the source establishes it.
2026-06 · June 2026 report: fifth-floor roof cast and sixth-floor works ongoing. The report includes April 2026 inspection evidence; this does not establish today’s status.
2026-06 · A report description, not a priced BOQ or accepted measurement book.
2026-06 · IMED report’s observations at that review. They do not establish current unresolved defects or corruption. Obtain correction and follow-up records.
12 April 2026 · Keep this positive result alongside defects. It is a report of limited sampled rebound tests, not a structural safety certification or acceptance of every item.
2026-06 · Dated report statement for the land component. The land-case number, parcel schedule, original handover and current development status are not established here.
2026-06 · Appendix planning fields, not the signed contract, measured area or actual dates. The procurement table elsewhere prints estimate 1813.08 lakh; the version difference needs approval records and is not evidence of an authorized variation.
4 April 2024 · A laboratory report retained inside IMED, not online authentication by BUET. Results apply to submitted samples; they do not establish the quality, identity or acceptance of every installed bar or the whole building.
7 August 2025 · The source building label differs from administrative building. Do not assign this test to WD-08 or certify all work. Sampling identity and laboratory authenticity need their own evidence.
Independent acceptance and the present condition are not established here. A dated resident observation appears in the conversation as a citizen account.
Thakurgaon college components described by IMED: administrative-building evidence and a separately identified land-acquisition component. Procurement links remain contextual candidates. Land expenditure is not a payment against the building contract; whole-programme amounts remain in their own dossier.
Location is recorded in the source; current conditions have not been independently inspected.
Thakurgaon engineering college: building, time and inspection
Planned quantities are separate from measured or accepted work.
These are questions to check. Missing records, money differences and reported completion do not establish corruption.
Some answers are shown here, and some held documents still need further extraction or review. Other records need a request to the holding office. The labels distinguish these situations; missing online does not mean unobtainable.
Office holding all of these: EED Thakurgaon Executive Engineer/accounts; DTE project office; Deputy Commissioner land branch for acquisition
The candidate tender notice records a BOQ Correction; its match to this IMED building still needs confirmation. The corrected file and accepted rates were not obtained.
Read the source date and scope with this finding. A retrieved summary is not the underlying signed account.
The named office is a collection route; custody, existence and disclosure of each missing file require confirmation. Missing records do not establish wrongdoing.
The candidate award proposes completion on 27 October 2026. Programme extension to June 2028 does not itself extend this building contract.
Read the source date and scope with this finding. A retrieved summary is not the underlying signed account.
The named office is a collection route; custody, existence and disclosure of each missing file require confirmation. Missing records do not establish wrongdoing.
Inspection findings and a 2024 steel test are held. The 2025 concrete test names the academic building, so it is not administrative-building acceptance.
Read the source date and scope with this finding. A retrieved summary is not the underlying signed account.
The named office is a collection route; custody, existence and disclosure of each missing file require confirmation. Missing records do not establish wrongdoing.
The report discusses running bills across four buildings, without a Thakurgaon bill split or signed certification sheets.
Read the source date and scope with this finding. A retrieved summary is not the underlying signed account.
The named office is a collection route; custody, existence and disclosure of each missing file require confirmation. Missing records do not establish wrongdoing.
Land acquisition has a separate reported amount. Building payments and the district share of programme transactions remain unverified.
Read the source date and scope with this finding. A retrieved summary is not the underlying signed account.
The named office is a collection route; custody, existence and disclosure of each missing file require confirmation. Missing records do not establish wrongdoing.
Exact identifiers and possible matches remain distinct, and a programme total is not this work’s share.
Contract amounts belong to their own packages. They are not additional project spending.
Administrative-building award, tender 867690
Possible match · needs reviewcontract-325034
Candidate contextual identity: same ten-storey Thakurgaon engineering-college building, MSCL-PCL JV and W-08/WD-08 package variant. Report does not print tender 867690, and dates/value differ.
Read each connection’s basis and scope before comparing amounts.
Possible match · needs reviewprogramme-224261500
Contextual match of full title, implementing agency and named four districts; no printed code in this report.
Whole-programme expenditure account
Possible match · needs reviewengineering-colleges-programme
Separate whole-programme financial scope from same IMED report.
Original documents · open a page to check the claim
…