কাজের হিসাব খুলছে…
কাজের হিসাব খুলছে…
Thakurgaon
Whole programme; the Thakurgaon share is not established.
Reported cumulative expenditure: ৳2,578,375,000 · 30 June 2026
78.65% · 30 June 2026
Payment and present condition remain separate questions.
Tangon, Buri and Bhully irrigation works · Questions, observations & replies
Loading source developments…
Approved plan · not spending or paymentWhole programme; the Thakurgaon share is not established.
Original June 2021 approved plan, not the current revised DPP, a contractor BOQ, measured delivery or executed payment.
Bar length compares each row with the largest row in this list. It is not a share or percentage of any total.
Component totals are not printed unit rates. The 44 original capital rows reconcile to the printed subtotal of 29,433.64 lakh Taka; this is planned-cost arithmetic only, not expenditure, payment or delivery verification.
The source gives no unit rates; none has been worked out by dividing a total.
Source 4Each row is as the source gives it. Rows are not added into a total.
Each step is a separate stage; amounts are never added together.
Estimate or approved cost
৳336.25 croreApproved project cost · ৳3,362,500,000 · Date not known · Whole projectFrom the FY2025–26 ADP edition; current revisions may differ.
Allocation
৳60.87 croreAnnual allocation · ৳608,700,000 · Date not known · 2026-27These are whole-programme figures, not Thakurgaon allocations, releases, paid bills or available cash. Spending through June 2025 cannot be subtracted from the 2026–27 allocation to calculate a remaining balance.
Funds released
Record not obtained · unknown is not zero
Contract
Record not obtainedSpending in a report
৳257.84 croreReported cumulative expenditure · ৳2,578,375,000 · 30 June 2026 · Cumulative through 30 June 2026BWDB’s parent table labels 25,783.75 lakh Taka as cumulative expenditure; its project-961 progress report dates the matching Total Financial amount to 30 June 2026. Whole-project reported expenditure/financial progress, not a register of executed payments or current cash.
Certified bill
Record not obtained · unknown is not zero
Payment made
Record not obtained · unknown is not zero
Original project approval in DPP
Source reportProject start in source
Source reportOriginal planned project completion
PlannedEighth implementation meeting scheduled
PlannedToday
Project end in source
Source reportA date in a report or certificate is not an inspection.
For safety, keep faces, house numbers and phone numbers out of photos and posts.
Every figure, date and document with its source. Open a topic to check it.
Separate financial stages · never added together
BWDB’s parent table labels 25,783.75 lakh Taka as cumulative expenditure; its project-961 progress report dates the matching Total Financial amount to 30 June 2026. Whole-project reported expenditure/financial progress, not a register of executed payments or current cash.
From the FY2025–26 ADP edition; current revisions may differ.
From the FY2025–26 ADP edition; current revisions may differ.
Reported revenue and capital expenditure combined; this is a historical cumulative figure.
These are whole-programme figures, not Thakurgaon allocations, releases, paid bills or available cash. Spending through June 2025 cannot be subtracted from the 2026–27 allocation to calculate a remaining balance.
These are whole-programme figures, not Thakurgaon allocations, releases, paid bills or available cash. Spending through June 2025 cannot be subtracted from the 2026–27 allocation to calculate a remaining balance.
These are whole-programme figures, not Thakurgaon allocations, releases, paid bills or available cash. Spending through June 2025 cannot be subtracted from the 2026–27 allocation to calculate a remaining balance.
These are whole-programme figures, not Thakurgaon allocations, releases, paid bills or available cash. Spending through June 2025 cannot be subtracted from the 2026–27 allocation to calculate a remaining balance.
FY2026–27 whole-project allocation category, not expenditure, release or payment. Revenue and capital are components of the already displayed annual allocation, not additional money.
Same limits as FY2026–27 revenue allocation above.
Original June 2021 approved plan, not the current revised DPP, a contractor BOQ, measured delivery or executed payment. Component totals are not printed unit rates.
Payment ledger incompleteCash balance unknown
Unknown payments are not zero. Differences between financial stages do not establish unspent or missing money. A comparable ledger and reconciliation are needed for a balance.
Original project approval in DPP Source reported
Date stated by the signed ministry certification, PDF page 3.Report date: 2021-06Project start in source Source reported
A dated source report, not an independent inspection, acceptance or executed-payment record.Original planned project completion Planned
Original June 2021 approved plan. This is not the current revised scope, a signed contractor BOQ, measured work or an executed payment.Report date: 2021-06Eighth implementation meeting scheduled Planned
The notice schedules a meeting. Attendance, minutes and action taken have not been collected.Report date: 24 February 2026Project end in source Source reported
A dated source report, not an independent inspection, acceptance or executed-payment record.A completed date field or certificate claim does not establish independent acceptance. An actual start or completion date is only identified when the source establishes it.
30 June 2026 · Whole-project physical progress reported by BWDB. It is not independent inspection or package-level acceptance.
2021-06 · Original June 2021 approved plan. This is not the current revised scope, a signed contractor BOQ, measured work or an executed payment.
2021-06 · Original June 2021 approved plan. This is not the current revised scope, a signed contractor BOQ, measured work or an executed payment.
Independent acceptance and the present condition are not established here. A dated resident observation appears in the conversation as a citizen account.
These are whole-programme figures, not Thakurgaon allocations, releases, paid bills or available cash. Spending through June 2025 cannot be subtracted from the 2026–27 allocation to calculate a remaining balance.
Location is recorded in the source; current conditions have not been independently inspected.
Rehabilitation of Tangoan Barage, Buri Bundh and Bhully Bundh Irrigation Projects, River Bank Protection and Construction of Combined Water Control Structure at Thakurgaon District. (1st Revised)
Planned quantities are separate from measured or accepted work.
These are questions to check. Missing records, money differences and reported completion do not establish corruption.
Some answers are shown here, and some held documents still need further extraction or review. Other records need a request to the holding office. The labels distinguish these situations; missing online does not mean unobtainable.
Office holding all of these: BWDB Thakurgaon O&M/project director; Mechanical O&M for pumps and hoists; project accounts
The original 2021 DPP brief and all 44 capital component costs are held; their arithmetic matches the original printed capital subtotal. Current revised scope, accepted item rates and signed BOQs are still needed.
Held June 2021 source reread on 10 October 2026; the source capture date remains 6 October 2026. This is not a current government-source refresh or a reviewed payment account.
The named office is a collection route; custody, existence and disclosure of each missing file require confirmation. Missing records do not establish wrongdoing.
Original June 2021 approved plan, not the current revised DPP, a contractor BOQ, measured delivery or executed payment. Component totals are not printed unit rates.
Original dates and a 2026 PIC meeting notice are held. A notice is not meeting minutes or approval of every package variation.
Read the source date and scope with this finding. A retrieved summary is not the underlying signed account.
The named office is a collection route; custody, existence and disclosure of each missing file require confirmation. Missing records do not establish wrongdoing.
BWDB reports 78.65% physical progress at 30 June 2026. Updated measurements, tests and accepted quantities require separate records.
Read the source date and scope with this finding. A retrieved summary is not the underlying signed account.
The named office is a collection route; custody, existence and disclosure of each missing file require confirmation. Missing records do not establish wrongdoing.
Reported financial progress at 30 June 2026 is BDT 2,578,375,000; it is not a set of certified package bills.
Read the source date and scope with this finding. A retrieved summary is not the underlying signed account.
The named office is a collection route; custody, existence and disclosure of each missing file require confirmation. Missing records do not establish wrongdoing.
The 25 exact project-code contract links identify procurement records. They cannot be summed into expenditure or executed payments.
Read the source date and scope with this finding. A retrieved summary is not the underlying signed account.
The named office is a collection route; custody, existence and disclosure of each missing file require confirmation. Missing records do not establish wrongdoing.
This applies to whole-project closure, not to existing bills or completed packages. It is a source-based assessment, not a statutory deadline.
Exact identifiers and possible matches remain distinct, and a programme total is not this work’s share.
Contract amounts belong to their own packages. They are not additional project spending.
Identifier matchedcontract-356717
Exact project code 224338700 and retained tender 823089 / package-lot 1274073. This award is not additive with project budget or reported expenditure.
Identifier matchedcontract-341269
Exact project code 224338700 and retained tender 846362 / package-lot 1306205. This award is not additive with project budget or reported expenditure.
Identifier matchedcontract-310803
Exact project code 224338700 and retained tender 853264 / package-lot 1319040. This award is not additive with project budget or reported expenditure.
Identifier matchedcontract-321134
Exact project code 224338700 and retained tender 853265 / package-lot 1319043. This award is not additive with project budget or reported expenditure.
Identifier matchedcontract-274267
Exact project code 224338700 and retained tender 941674 / package-lot 1466294. This award is not additive with project budget or reported expenditure.
Identifier matchedcontract-105783
Exact project code 224338700 and retained tender 1173078 / package-lot 1844784. This award is not additive with project budget or reported expenditure.
Identifier matchedcontract-106714
Exact project code 224338700 and retained tender 1173080 / package-lot 1844783. This award is not additive with project budget or reported expenditure.
Identifier matchedcontract-11217
Exact project code 224338700 and retained tender 1268624 / package-lot 2018390. This award is not additive with project budget or reported expenditure.
Identifier matchedcontract-899730
Exact project code 224338700 and retained tender 1291943 / package-lot 2052611. This award is not additive with project budget or reported expenditure.
Identifier matchedcontract-444785
Exact project code 224338700 and retained tender 683421 / package-lot 1071446. This award is not additive with project budget or reported expenditure.
Identifier matchedcontract-444777
Exact project code 224338700 and retained tender 683423 / package-lot 1071306. This award is not additive with project budget or reported expenditure.
Identifier matchedcontract-444774
Exact project code 224338700 and retained tender 683424 / package-lot 1071383. This award is not additive with project budget or reported expenditure.
Identifier matchedcontract-444765
Exact project code 224338700 and retained tender 683425 / package-lot 1071450. This award is not additive with project budget or reported expenditure.
Identifier matchedcontract-444640
Exact project code 224338700 and retained tender 683427 / package-lot 1071453. This award is not additive with project budget or reported expenditure.
Identifier matchedcontract-443466
Exact project code 224338700 and retained tender 683428 / package-lot 1071670. This award is not additive with project budget or reported expenditure.
Identifier matchedcontract-442099
Exact project code 224338700 and retained tender 683429 / package-lot 1071457. This award is not additive with project budget or reported expenditure.
Identifier matchedcontract-426233
Exact project code 224338700 and retained tender 706646 / package-lot 1101036. This award is not additive with project budget or reported expenditure.
Identifier matchedcontract-426094
Exact project code 224338700 and retained tender 706647 / package-lot 1101053. This award is not additive with project budget or reported expenditure.
Identifier matchedcontract-421085
Exact project code 224338700 and retained tender 706648 / package-lot 1101050. This award is not additive with project budget or reported expenditure.
Identifier matchedcontract-417817
Exact project code 224338700 and retained tender 706649 / package-lot 1101055. This award is not additive with project budget or reported expenditure.
Identifier matchedcontract-417692
Exact project code 224338700 and retained tender 726556 / package-lot 1130356. This award is not additive with project budget or reported expenditure.
Identifier matchedcontract-414759
Exact project code 224338700 and retained tender 729852 / package-lot 1136904. This award is not additive with project budget or reported expenditure.
Identifier matchedcontract-416651
Exact project code 224338700 and retained tender 737168 / package-lot 1149422. This award is not additive with project budget or reported expenditure.
Identifier matchedcontract-404992
Exact project code 224338700 and retained tender 749185 / package-lot 1165883. This award is not additive with project budget or reported expenditure.
Identifier matchedcontract-404875
Exact project code 224338700 and retained tender 755036 / package-lot 1173030. This award is not additive with project budget or reported expenditure.
Planned purchases and quantities. A plan does not prove an award, delivery or payment.
Possible match · needs reviewplan-386906
The APP row prints the same full project title; APP 179641, package 656502, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386907
The APP row prints the same full project title; APP 179641, package 656507, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386910
The APP row prints the same full project title; APP 179641, package 656509, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386912
The APP row prints the same full project title; APP 179641, package 656511, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386914
The APP row prints the same full project title; APP 179641, package 656512, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386916
The APP row prints the same full project title; APP 179641, package 656513, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386918
The APP row prints the same full project title; APP 179641, package 656514, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386920
The APP row prints the same full project title; APP 179641, package 656515, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386922
The APP row prints the same full project title; APP 179641, package 656516, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386924
The APP row prints the same full project title; APP 179641, package 697912, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386925
The APP row prints the same full project title; APP 179641, package 697926, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386926
The APP row prints the same full project title; APP 179641, package 697930, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386928
The APP row prints the same full project title; APP 179641, package 697933, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386930
The APP row prints the same full project title; APP 179641, package 697937, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386933
The APP row prints the same full project title; APP 179641, package 697947, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386934
The APP row prints the same full project title; APP 179641, package 697956, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386937
The APP row prints the same full project title; APP 179641, package 729111, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386939
The APP row prints the same full project title; APP 179641, package 729132, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386941
The APP row prints the same full project title; APP 179641, package 729181, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386944
The APP row prints the same full project title; APP 179641, package 729184, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386946
The APP row prints the same full project title; APP 179641, package 729185, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386947
The APP row prints the same full project title; APP 179641, package 729187, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386949
The APP row prints the same full project title; APP 179641, package 729384, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386953
The APP row prints the same full project title; APP 179641, package 749798, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386954
The APP row prints the same full project title; APP 179641, package 749805, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386957
The APP row prints the same full project title; APP 179641, package 749813, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386959
The APP row prints the same full project title; APP 179641, package 749818, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386961
The APP row prints the same full project title; APP 179641, package 749829, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386962
The APP row prints the same full project title; APP 179641, package 749831, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386966
The APP row prints the same full project title; APP 179641, package 749835, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386968
The APP row prints the same full project title; APP 179641, package 749837, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386970
The APP row prints the same full project title; APP 179641, package 750307, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386972
The APP row prints the same full project title; APP 179641, package 750314, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386974
The APP row prints the same full project title; APP 179641, package 750369, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-386976
The APP row prints the same full project title; APP 179641, package 750380, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Repair of Vehicles of jeep no Dhaka Metro Gha 15-2221.
Possible match · needs reviewplan-411995
The APP row prints the same full project title; APP 210825, package 1149911, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-411997
The APP row prints the same full project title; APP 210825, package 1149913, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Printing and binding of different reports, DPP etc.
Possible match · needs reviewplan-411999
The APP row prints the same full project title; APP 210825, package 1149914, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-412000
The APP row prints the same full project title; APP 210825, package 1149924, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-412002
The APP row prints the same full project title; APP 210825, package 1155570, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Supply of Multimedia Projector 01 nos
Possible match · needs reviewplan-412003
The APP row prints the same full project title; APP 210825, package 1192317, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Agriculturial Farm Demonistration
Possible match · needs reviewplan-423362
The APP row prints the same full project title; APP 211423, package 1164234, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Water Management Organization Formation, Field Day at Tangon, Buri, Vulli Project
Possible match · needs reviewplan-423363
The APP row prints the same full project title; APP 211423, package 1168427, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Farmers Training program at Tangon, Buri, Vulli Project
Possible match · needs reviewplan-423364
The APP row prints the same full project title; APP 211423, package 1168516, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-499150
The APP row prints the same full project title; APP 183489, package 717984, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-499153
The APP row prints the same full project title; APP 183489, package 717989, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-499156
The APP row prints the same full project title; APP 183489, package 770060, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-499160
The APP row prints the same full project title; APP 183489, package 798465, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-637911
The APP row prints the same full project title; APP 187222, package 1007808, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-637912
The APP row prints the same full project title; APP 187222, package 776198, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-637913
The APP row prints the same full project title; APP 187222, package 784686, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-637914
The APP row prints the same full project title; APP 187222, package 796682, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-637915
The APP row prints the same full project title; APP 187222, package 801053, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-637916
The APP row prints the same full project title; APP 187222, package 842659, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-637917
The APP row prints the same full project title; APP 187222, package 849438, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-637918
The APP row prints the same full project title; APP 187222, package 849442, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-637919
The APP row prints the same full project title; APP 187222, package 849450, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-637920
The APP row prints the same full project title; APP 187222, package 849455, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-637921
The APP row prints the same full project title; APP 187222, package 850014, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-637922
The APP row prints the same full project title; APP 187222, package 850028, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-637923
The APP row prints the same full project title; APP 187222, package 850042, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-637924
The APP row prints the same full project title; APP 187222, package 850071, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-637925
The APP row prints the same full project title; APP 187222, package 850075, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-637926
The APP row prints the same full project title; APP 187222, package 850077, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-637927
The APP row prints the same full project title; APP 187222, package 850080, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-637928
The APP row prints the same full project title; APP 187222, package 850084, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-637929
The APP row prints the same full project title; APP 187222, package 866972, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-637930
The APP row prints the same full project title; APP 187222, package 870721, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-737670
The APP row prints the same full project title; APP 189542, package 806143, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-737671
The APP row prints the same full project title; APP 189542, package 806188, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-737672
The APP row prints the same full project title; APP 189542, package 849005, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-777293
The APP row prints the same full project title; APP 218148, package 1245529, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-777294
The APP row prints the same full project title; APP 218148, package 1370638, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Training program at Tangon , Buri and Vulli Irrigation Project
Possible match · needs reviewplan-781016
The APP row prints the same full project title; APP 218415, package 1358664, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-788052
The APP row prints the same full project title; APP 218917, package 1258666, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-788053
The APP row prints the same full project title; APP 218917, package 1258673, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-911596
The APP row prints the same full project title; APP 194788, package 1030413, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-911597
The APP row prints the same full project title; APP 194788, package 1068932, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-911598
The APP row prints the same full project title; APP 194788, package 902434, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-911599
The APP row prints the same full project title; APP 194788, package 902437, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-911600
The APP row prints the same full project title; APP 194788, package 963758, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-911601
The APP row prints the same full project title; APP 194788, package 963770, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-911602
The APP row prints the same full project title; APP 194788, package 982937, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-911603
The APP row prints the same full project title; APP 194788, package 983673, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-911604
The APP row prints the same full project title; APP 194788, package 983678, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-911605
The APP row prints the same full project title; APP 194788, package 983684, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Seminar on Tangon, Buri and Vulli Project
Possible match · needs reviewplan-1109229
The APP row prints the same full project title; APP 199144, package 1028230, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Farmers Skill development Training program on water Management.
Possible match · needs reviewplan-1109230
The APP row prints the same full project title; APP 199144, package 948809, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-1109231
The APP row prints the same full project title; APP 199144, package 949377, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Possible match · needs reviewplan-1109232
The APP row prints the same full project title; APP 199144, package 957286, source grain Package. No project code is printed in this retained plan row. This is project context, not a proved plan-to-contract join or verified delivery location. Planning estimates, awards and expenditure are not added.
Read each connection’s basis and scope before comparing amounts.
Same project code in another retained record
Identifier matchedprogramme-224338700
Exact project code; versions and amounts are not additive
Original documents · open a page to check the claim
…