Thakurgaon
Whole programme; the Thakurgaon share is not established.
Component-table cumulative total as printed: ৳1,148,635,000 · May 2026
Approximately 25% · April 2026
Payment and present condition remain separate questions.
Four engineering colleges: reported spending and delivery · Questions, observations & replies
Loading source developments…
These lists may hold the same money. Do not add them.
Spending as the source reports it · not proof of paymentCumulative through May 2026Whole programme; the Thakurgaon share is not established.
The rows the source lists, not a complete or reconciled breakdown. Each row has its own limits.
IMED table 3.2 cumulative financial column through May 2026, lakh Taka converted to BDT. Whole four-college programme revenue category, not a Thakurgaon share, certified bill or executed payment. These components overlap the reported programme total.
IMED table 3.2 cumulative financial column through May 2026, lakh Taka converted to BDT. Whole four-college programme revenue category, not a Thakurgaon share, certified bill or executed payment. These components overlap the reported programme total.
Bar length compares each row with the largest row in this list. It is not a share or percentage of any total.
The period or stage differs.
Separate audit narrative for four administrative buildings through EED, described as mostly spent in FY 2024–25; no common cutoff or building-wise split is printed. This reported running-bill aggregate is not an executed-payment ledger, certified bill population or Thakurgaon amount. It overlaps programme accounts and must not be added to tables 3.1/3.2.
Each row is as the source gives it. Rows are not added into a total.
Each step is a separate stage; amounts are never added together.
Estimate or approved cost
৳1621.24 croreRevised whole-programme cost · ৳16,212,375,000 · Date not known · Second revision; whole projectA source-reported amount, not independently verified executed payments. Do not add cumulative and annual figures, or components and their totals.
Funds released
Record not obtained · unknown is not zero
Contract
Record not obtainedSpending in a report
৳114.86 croreComponent-table cumulative total as printed · ৳1,148,635,000 · May 2026 · Through May 2026Whole-programme component total; different from table 3.1. Periods and source inconsistencies remain visible; this is not a Thakurgaon or contract payment total.
Certified bill
Record not obtained · unknown is not zero
Payment made
Record not obtained · unknown is not zero
Today
A date in a report or certificate is not an inspection.
For safety, keep faces, house numbers and phone numbers out of photos and posts.
Every figure, date and document with its source. Open a topic to check it.
Separate financial stages · never added together
Whole-programme component total; different from table 3.1. Periods and source inconsistencies remain visible; this is not a Thakurgaon or contract payment total.
A source-reported amount, not independently verified executed payments. Do not add cumulative and annual figures, or components and their totals.
The annual rows add to 11,481.57 lakh, while the source total prints 11,481.67 lakh. Retained as a source discrepancy, not a reconciled total.
The required evidence has not been collected. Unknown does not mean zero.
Payment ledger incompleteCash balance unknown
Unknown payments are not zero. Differences between financial stages do not establish unspent or missing money. A comparable ledger and reconciliation are needed for a balance.
The start order, original deadline, approved extensions and acceptance record are needed.
A completed date field or certificate claim does not establish independent acceptance. An actual start or completion date is only identified when the source establishes it.
Date not established · Month precision retained. An approved implementation period is not proof of actual completion.
2026-06 · Attributed reported settlement; original challans and settlement orders are not held. Repeated BDT 34,935 entries are not summed because their economic identity is unresolved. This corrects the earlier four-row summary.
2026-06 · Whole-programme status in the June 2026 report, not a current count or independent completion verification. Counts are packages, not bills or distinct completed colleges.
2026-06 · An attributed IMED assessment of goods packages, not WD-08. The implementing agency response and underlying approvals have not been obtained. This is not a court decision or a DeshLoop corruption finding.
2026-06 · Planning evidence for four colleges. It is not a signed priced BOQ, completed output, release order or payment. The signed latest RDPP and annexes remain necessary to confirm the approved version.
2026-04 · IMED sections 5.1/5.2 attribute this approximate physical-progress figure to the whole four-college programme, alongside financial reporting through April 2026. It is not the separate Thakurgaon building-progress figure or an independently measured result.
Independent acceptance and the present condition are not established here. A dated resident observation appears in the conversation as a citizen account.
Whole four-college programme covering Khagrachhari, Narail, Naogaon and Thakurgaon. No Thakurgaon spending split or payment ledger is established.
These figures cover the whole programme. They are not a Thakurgaon allocation or expenditure total.
Four engineering colleges: reported spending and delivery
Planned quantities are separate from measured or accepted work.
These are questions to check. Missing records, money differences and reported completion do not establish corruption.
Some answers are shown here, and some held documents still need further extraction or review. Other records need a request to the holding office. The labels distinguish these situations; missing online does not mean unobtainable.
Office holding all of these: Four Engineering Colleges project director, DTE; TMED development branch; EED accounts; audit custodian
Programme procurement and work plans are held; plan totals and consulting person-months are not accepted unit prices or delivered work.
Read the source date and scope with this finding. A retrieved summary is not the underlying signed account.
The named office is a collection route; custody, existence and disclosure of each missing file require confirmation. Missing records do not establish wrongdoing.
Held report availability is separate from obtaining original signed transaction records.
The report gives programme revisions and follow-up recommendations. Contract-specific extensions and signed decisions still need collection.
Read the source date and scope with this finding. A retrieved summary is not the underlying signed account.
The named office is a collection route; custody, existence and disclosure of each missing file require confirmation. Missing records do not establish wrongdoing.
Building progress and inspection findings are held. District/package measurement books and signed acceptance are missing.
Read the source date and scope with this finding. A retrieved summary is not the underlying signed account.
The named office is a collection route; custody, existence and disclosure of each missing file require confirmation. Missing records do not establish wrongdoing.
Five audit observations are reported settled. The report also mentions BDT 208.1 million in running bills for four buildings; it supplies neither complete bills nor a common cutoff.
Read the source date and scope with this finding. A retrieved summary is not the underlying signed account.
The named office is a collection route; custody, existence and disclosure of each missing file require confirmation. Missing records do not establish wrongdoing.
Annual/category spending and some land figures are held. Blank payment forms are not filled transaction records, and programme totals cannot be assigned to Thakurgaon.
Read the source date and scope with this finding. A retrieved summary is not the underlying signed account.
The named office is a collection route; custody, existence and disclosure of each missing file require confirmation. Missing records do not establish wrongdoing.
This applies to whole-project closure, not to existing bills or completed packages. It is a source-based assessment, not a statutory deadline.
Exact identifiers and possible matches remain distinct, and a programme total is not this work’s share.
Read each connection’s basis and scope before comparing amounts.
Four engineering colleges programme 224261500
Possible match · needs reviewprogramme-224261500
Reviewed contextual identity: full programme title, four named districts and implementing agency agree; IMED PDF does not print this project code.
Thakurgaon component inspection
Possible match · needs reviewthakurgaon-engineering-college
Explicit Thakurgaon section in the same monitoring report.
Original documents · open a page to check the claim
…