Reported financial progress৳18,319,000
Source reports: 100% · 26 July 2026Complete payment account not held

Work location in the source: Thakurgaon Sadar

Acceptance and the present condition need separate evidence.

What remains unknown

We do not have records showing who was paid, when and how much.

Acceptance and the present condition need separate evidence.

The current balance is unknown.

Reported cumulative expenditure৳2,578,375,000
Source reports: 78.65% · 30 June 2026Complete payment account not held

Whole programme; the Thakurgaon share is not established.

Acceptance and the present condition need separate evidence.

What remains unknown

We do not have records showing who was paid, when and how much.

Acceptance and the present condition need separate evidence.

The current balance is unknown.

Administrative-building contract value in report৳163,165,900
Source reports: 50% · June 2026Complete payment account not held

The Thakurgaon college component only.

Acceptance and the present condition need separate evidence.

What remains unknown

We do not have records showing who was paid, when and how much.

Acceptance and the present condition need separate evidence.

The current balance is unknown.

Component-table cumulative total as printed৳1,148,635,000
Source reports: Approximately 25% · April 2026Complete payment account not held

Whole programme; the Thakurgaon share is not established.

Acceptance and the present condition need separate evidence.

What remains unknown

The source figures need explanation; they do not give a complete payment account.

Acceptance and the present condition need separate evidence.

The current balance is unknown.

Search held government records ↗