Supply, Installation, Testing & Commissioning of 11/0.415 KV, 1250 KVA Substation for 6-Storied Library Building at Jahangirnagar University, Savar Upazila,Dhaka District.
Published tender notice; contract price not obtained. Scope and financial stage follow the source.
Primary record inspected
The money, with its exact meaning
Fee / rate
Tender document price
৳4,000.00Price to purchase the tender document; not contract cost, total collections or student fees.
e-GP tender 1330885Tender security
Tender security — lot WD-01
৳9,50,000.00Bid security required by the published notice; not project cost, award price or paid spending.
e-GP tender 1330885These figures are separate source statements. No remaining balance, payment ledger or total across stages is inferred.
Scope and responsibility
- Named office
- Office of the Executive Engineer, EED, Dhaka, District. — Education Engineering Department
- Source date
- 10 Sept 2026
- Recorded status
- Being processed
- Annual procurement plan ID
- 222278
- Budget type
- Development
- Funding source
- Government
- Lot 1: ID
- WD-01
- Lot 1: tentative completion date
- 2027-06-03
- Lot 1: tentative start date
- 2026-12-06
- Memo reference
- 37.07.0000.000.016.14.0004.25.3 dt:01.01.2026
- Organization
- Education Engineering Department
- Package
- EED/Dhaka/F.D.JU Project/Substation/2025-26/WD-01
- Procurement method
- Open Tendering Method (OTM)
- Project code
- 224268000
- Project name
- Further Development of Jahangirnagar (JU) University Project.
- Scope
- university-or-campus-project
- Tender status stated in source
- Being processed
- Tender closing date
- 2026-09-24
- Tender ID
- 1330885
- Tender publication date
- 2026-09-10
- Places named
- Library
A source date is not necessarily an event date. A named place or office does not establish every funding relationship or current service condition.
Connected records
Connected by an explicit reference or matching tender or project identifier. This does not by itself prove a flow of funds.
Development projects · —Further Development of Jahangirnagar University · approved project scopeDevelopment projects · 2021-222021-22 · RADP allocation for Further DevelopmentDevelopment projects · 2022-232022-23 · ADP allocation for Further DevelopmentDevelopment projects · 2022-232022-23 · RADP allocation for Further DevelopmentDevelopment projects · 2023-242023-24 · ADP allocation for Further DevelopmentDevelopment projects · 2024-252024-25 · RADP allocation for Further DevelopmentDevelopment projects · 2025-262025-26 · ADP allocation for Further DevelopmentDevelopment projects · —Further Development · reported progress through December 2022Questions and evidence
Loading contributions…